VANDERBILT LAKES COMMUNITY SERVICES ASSOCIATION

VCSA LAKE BANK RESTORATION PILOT  10-24-17 Report

The Lake Bank Restoration Pilot (approved at the May 2, 2017 VCSA Board of Directors meeting) was conducted during the last weeks of May at 3780 Saybrook Place.  The purpose of the pilot was to evaluate the compacted aggregate / littoral solution for gradual lake slope drop-offs, with escarpments exceeding SFWMD criteria of 9” – 10”.  This condition is characteristic of the majority of the roughly two-mile Vanderbilt Lake shoreline.

The lake bank was restored to a 4:1 slope from the existing 16” escarpment to 2 feet below the normal low water line as permitted using compacted aggregate fill.  Stone of varying size was embedded in the lake bed, at a point 2 feet below waterline, to provide a toe hold to prevent fill from receding into the lake.  Drainage lines were routed from gutter downspouts into the lake below the water line.  The finished slope was covered with Turf Reinforcement Mat, and secured with J rebar hooks and 6”  staples.

When installation was complete, the dry season was still in place.  The historically low lake level and lack of rain prevented planting of littorals.  Later in June, 15” of rain fell in three days.  The lake overfilled its banks and remained high through the ensuing 2017 summer rainy season.  Littorals will be planted as the water level recedes exposing more bank.

Several outstanding issues will need further evaluation and resolution before the pilot is considered an unqualified success.  One issue encountered was the Turf Reinforcement Mat floating to the surface due to the rapid rise in lake level.  The  contractor will come back and reattach the mat with J hooks or equivalent that provide greater gripping power to the compacted aggregate.  Also, evaluation of littorals will be made over the course of the dry season as progressive plantings are completed.  Despite the lack of littoral plantings, there is no visible erosion.  This condition will be monitored during the dry season as the water level recedes and more of the restored slope becomes visible.

Photos (23) of the restoration pilot are attached.  They show the various stages of the Pilot Bank Restoration Project as presented at the VCSA BOD 10-24-17 meeting.

 

 

 

 

 

 

 

 

 

 

 

Completed 4:1 Slope Viewed From Common’s Area and Essex Place: 2 photos

c9ead4c9906763b5-photo.JPG

ae1c211df5c5f78e-photo.JPG

 Original 16” Shoreline Escarpment: 2 photos

ca19a474104e04ce-photo.JPG

a6d39ab8a453291e-photo.JPG

Staging in Saybrook Cul de Sac: 2 photos

5b5ad39a46f56a9b-photo.JPG

9e46d6aad203e3ea-photo.JPG

Access Through Pilot Property Front Yard and Sideyard Utility Right of Way: 3 photos

195490d39ef77d8a-photo.JPG

ea3e4173d16ca5fa-photo.JPG

97dc6a5cfdf4f8fa-photo.JPG

 

 

 

 

Drainage Lines From All Three Lake Facing Gutter Downspouts : 1 photo showing method

2e72558bc53caa9b-photo.JPG

 

 

 

 

 

 

 

 

 

 

 

 

 

4:1 Slope Restoration Starting at Existing Escarpment: 6 photos

0df64a36667965d7-photo.JPG

944ac3a01ed26509-photo.JPG

d1e84bcc19119032-photo.JPG

05830a45b9ed2aef-photo.JPG

 

3a0751455f632d26-photo.JPG

4991a0fcccb95518-photo.JPG

 

Turf Reinforcement Mat & Sod Installation: 7 photos including access path resod

0734572cb6fbcf35-photo.JPG

ec7e5eb6d3c64adc-photo.JPG

1d0f116d422b1d56-photo.JPG

b39fa76be0b139b4-photo.JPG

129407e2601f18e9-photo.JPG

72d396fde8b204da-photo.JPG

 

65c9c9e34463e362-photo.JPG